Bond Measures - Previous Projects

PREVIOUS PROJECTS

The following 2017 summer modernization projects are part of the $298M CUSD Bond Measure that was approved by the community in 2012.  We thank our community for their continued efforts to provide financial support to build quality educational facilities for our students, teachers and communities.

LINKS

Buchanan High School

Major ComponentsEstimated Completion
Counseling Center remodelOct 2017
Library remodelOct 2017
Renovate poolOct 2017
Pool restrooms additionOct 2017
Door hardware replacement at gyms and academic wingSept 2017
Add Extron systems (AV systems) in classrooms, LMC, MPRAug 2017
Paint interior hallwaysAug 2017
Locker room improvements (ceiling, minor flooring changes in coaches office, paint)Aug 2017
Data and power upgrades throughout campusAug 2017
Site floor replacement- carpet, polished concrete (Academic hallway, business bldg, MPR)Aug 2017
Site roofing replacement (exc. LMC)Sept 2017
ADA drinking fountainsAug 2017
Landscape and irrigation improvementsAug 2017
Minor casework improvementsAug 2017
Site concrete improvementsOct 2017
Sitting areas at locker baysAug 2017
ADA accessibility upgradesAug 2017

Buchanan High School – Pool
Buchanan High School – Pool

Way-finding Hallways

Pool Restrooms
Multipurpose Floor
Multipurpose Floor
Counseling Work Station
Counseling Work Station
Career Center & Counseling Center
Career Center & Counseling Center

Bud Rank

Major ComponentsEstimated Completion
Minor exterior lightingAug 2017
Add Extron systems (AV systems) in selected classrooms, LMC, MPR, Kindergarten, and computer labAug 2017
TV Monitor and PA speakers in LMC, conf. roomAug 2017
Wireless upgrade in all classroomsAug 2017
New sound system in MPRAug 2017
Reading room in LMCAug 2017

Nurse Office
Nurse Office
Classroom Audio Visual
Classroom Audio Visual

Clark Intermediate

Major ComponentsEstimated Completion
Choir room additionOct 2017
Learning Director office relocation and remodelAug 2017
Drama prop production canopy additionSept 2017

Learning Director Office
Learning Director Office
Classroom
Classroom
Landscape
Landscape
Choir Room
Choir Room

Clovis Elementary

Major ComponentsEstimated Completion
HVAC/ Chiller replacementAug 2017
Additional casework and ADA sinks at all classroomsAug 2017
Add Extron systems (AV systems) in classrooms, LMC, MPR and computer labAug 2017
Reading room at LMCAug 2017
New sound equipment at MPRAug 2017
Fire alarm replacementAug 2017
Replace clocks, PA, EMS systemAug 2017
Data room upgradeAug 2017
Window treatment at West Admin buildingAug 2017
Administration remodel – add conference room; upgrade flooring, lighting and caseworkAug 2017
Reconfigure nurse’s officeAug 2017
Minor restroom upgradesAug 2017
ADA accessibility upgradeSept 2017

Reading Room Area
Reading Room Area
Administration Building Conference Room
Administration Building Conference Room
Administration Entry
Administration Entry
Classroom HVAC
Classroom HVAC

Clovis North Educational Center

Major ComponentsEstimated Completion
Counseling Center remodelOct 2017
Seating benches and drainage at amphitheaterAug 2017
Tree and Landscaping in amphitheatersAug 2017
Add Extron systems (AV systems) at LMC, selected classrooms, MPR’s, and music roomsAug 2017
Data drops at gymnasiumsAug 2017
UPS power at racksAug 2017
ADA restroom upgradesAug 2017

Counseling Center Hallway
Counseling Center Hallway
Field Lighting
Field Lighting
Counseling Center Signage
Counseling Center Signage
Amphitheater Seating/New Drainage
Amphitheater Seating/New Drainage

District Office Final Phase

Major ComponentsEstimated Completion
Remodel of Professional Development Building – staff development/boardroomOct 2017
Professional Development Building flooring replacementSept 2017
Professional Development Building reconfiguration of lobby and reception deskOct 2017
Maintenance and Operations bathroom additionDec 2017
Transportation restroom upgradeDec 2017
Transportation dispatch remodelDec 2017
Maintenance/Transportation Building HVAC replacement, flooring, lighting, wall and ceiling upgradesDec 2017
Grounds Building upgrades- flooring, expansion of computer work station room, replace roofingAug 2017
SSSA flooring and lighting upgradesNov 2017
District Services flooring upgrades, IDU addition in computer roomJan 2017
Exterior parking lighting at DO East and DO WestDec 2017
DO East reconfiguration of lobby and reception deskJune 2017
DO East office reconfigurationsJune 2017
DO West expansion of lobby and reception deskSept 2017
DO West remodel restroom facilitiesJune 2017
DO West office reconfigurationsSept 2017
Remodel of Northwest corner of buildingJune 2017

Restroom
Restroom
Professional Development Building New Carpet
Professional Development Building New Carpet
Payroll Workstation
Payroll Workstation
Grounds Workroom
Grounds Workroom
New Conference Room
New Conference Room
District Office West Entry
District Office West Entry
District Office West Receptionist Area
District Office West Receptionist Area
Budget Finance Workstations
Budget Finance Workstations

Lincoln

Major ComponentsEstimated Completion
Expansion and complete modernization of MPR (HVAC, ceilings, walls, sound system, AV controls, lighting, toilet rooms, fire sprinkler system)Oct 2017
Expansion and modernization of Admin and LMC building (added conference and textbook storage , expansion of nurse’s office, lighting, ceiling, walls, and HVAC upgrades)Oct 2017
Roofs on buildings 20,30; Kindergarten and Building 10Aug 2017
Snack Bar restroom upgradeAug 2017
Add Extron systems (AV systems) in classroomsAug 2017
Add Extron systems at LMC and MPRAug 2017
Classroom casework refurbishAug 2017
Classroom lamp upgradesAug 2017
Replace clocks and PA systemAug 2017

Administration Reception Area
Administration Reception Area
Administration Building
Administration Building
Multipurpose Room
Multipurpose Room
Nurse’s Office
Nurse’s Office
Kitchen Serving Window
Kitchen Serving Window
Library Reading Room
Library Reading Room

Reagan Elementary

Major ComponentsEstimated Completion
Add Extron systems (AV systems) in classrooms, LMC, MPR and computer labAug 2017
Minor exterior lighting (2 poles at Kdg. Area)Aug 2017
Computer lab upgradeAug 2017
Reading room at LMCAug 2017
New casework in LMC for text storageAug 2017

Library Media Storage
Library Media Storage
Reading Area
Reading Area
Kindergarten Classroom Audio Visual
Kindergarten Classroom Audio Visual
Computer Lab
Computer Lab

Woods Elementary

Major ComponentsEstimated Completion
Add Extron systems (AV systems) in classrooms, LMC, MPR and computer lab (white board realignment)Aug 2017
Reading room addition in LMCAug 2017
AV system in classrooms, computer lab, LMC, MPRAug 2017
Additional work station in Nurse’s officeAug 2017

Computer Lab
Computer Lab

Clovis Unified School District: Be the best you can be in mind, body, and spirit

Buchanan Area Schools

Buchanan Alta Sierra Cole Century Dry Creek Garfield Tarpey Woods

Clovis High Area Schools

Clovis High Clark Cedar Wood Mickey Cox Gettysburg Jefferson Red Bank Sierra Vista Weldon Clovis Elementary

Clovis West Area Schools

Clovis West Kastner Ft. Washington Liberty Lincoln Maple Creek Nelson Pinedale Valley Oak

Clovis North Area Schools

Clovis North Bud Rank Copper Hills Fugman Mountain View River View

Clovis East Area Schools

Clovis East Boris Fancher Creek Freedom Miramonte Oraze Temperance Kutner Reagan Elementary

More Schools

CART Gateway Clovis Online School Clovis Community Day School Clovis Adult Education Sierra Outdoor